Task Numbering
The default operation is to number tasks sequentially, running from the upper left hand corner to the lower right-hand corner of the Planning View. The program provides two additional methods for numbering tasks, for projects where it is desired to organize groups of tasks using an outline. To switch between the numbering modes, use the menu entries for Options and Overall and Task Numbering Style. The three methods are
- Numbers (the default)
- Outline
- Outline with indenting
In the Outline method, each row is assigned a number. The text in the "Project Outline" column serves as a name for the activities in the row. The first row in the Example below is "1.", it's name is "Row 1" and individual tasks in the row are then numbered 1.1, 1.2, etc See the example below. Row 2 is "2." tasks in Row 2 are 2.1, 2.2, 2.3 etc.

In Planning View;

As it appears in the Timeline View;
|